Independent field tool. Verify against current NEC and local AHJ.
Not a substitute for professional engineering judgment.
Phase & Circuit Mapper
Map circuits · analyze imbalance
System
Phase Legend
Lookup
Panel Layout
Standard A-B-C vertical bus · rows 1-2, 3-4, 5-6…
Assumes standard A-B-C vertical bus sequence. Verify markings on your panel before working it.
Analyzer
Readings
---
NEMA MG-1 imbalance method. Motor commissioning and panel balancing helper.
Always verify with calibrated meters and AHJ requirements.
🔢
Bending Master
Hand-bender suite · EMT, IMC, RMC
Enter amps, distance, and voltage to calculate drop
Notes: kVA ignores PF. For kW/W calculations, enter PF (typical motors ~0.85–0.92).
Enter voltage and either amps or watts to convert
Enter kVA to size secondary amps
Pick HP and voltage/phase to pull NEC FLA
Enter load amps to size OCPD or conductor
CONTINUOUS LOAD (×125%)
APPLY “SMALL CONDUCTOR” CAP (Cu #14/#12/#10)
Field helper only. Verify derating, terminations, and your adopted NEC edition.
Enter breaker rating to find min conductor
CONTINUOUS LOAD (125%)
DWELLING SERVICE/FEEDER (83% · NEC 310.12)
Enter feeder OCPD to size home feeder conductor
Count each wire that comes in from outside the box. A wire that loops through unspliced counts 1, or 2 if the loop is 12" or longer.
A device wider than one gang counts as one yoke for each gang it takes.
Enter box volume and conductor counts for fill
Dwelling Info
Fixed Appliances (VA)
NEC 220.53 · 75% demand factor applied when 4 or more fixed appliances are on the feeder.
Cooking · Dryer
Range per NEC 220.55 Col C. Dryer per NEC 220.54.
HVAC · EV
HVAC noncoincident per NEC 220.60. EV per Art. 625 & 220.57.
Fill the dwelling form to calculate service load
🧱
Concrete
Trench · Pole · Slab · yd³ + bags + cost
Trench
Pole / Footing
Slab (Multi)
CONDUIT / DUCT BANK
Round = outside diameter. Square = side width (a 4×4 is 3.5").
🛠
Field Hacks
Tools no one thinks about · until they need them
Pipe Marker
Finding GPS…
Hold still over the pipe…
± – ft–
Averaging GPS readings — the longer you hold, the steadier the spot.
Tap the map where the pipe is
Zoom in close first. You can tap again to move it.
Pin details
Tape ties — best way to find it again
Measure from 2 things that won’t move (corner of a pad, hydrant, pole, building corner).
A
B
Finding
—
—
—
Saved Pins
Spool Calculator
1What’s on the spool?
2How long was the full spool?
feet
3How did you hook up your meter?
4What does your meter read?
Match the unit on your meter’s screen: mΩ or Ω. (1,000 mΩ = 1 Ω.) Zero your leads first if your meter can.
Fine-tune (wire temperature & resistance)
Leave these alone unless you know better. Wire temp is the conductor’s actual temperature (a spool in the sun runs hot) — not the insulation rating. Ω per 1000 ft fills in from the wire size at 20°C; change it only if the cable’s spec sheet says different.
Survey Helper
—
Use station format like 10+25, 10+25.5, or 0+75.
—
Enter total feet and convert it to station format.
—
—
Midpoint Station
—
—
Decimal ↔ Tape
Tape Measure
—
—
Decimal Feet
—
—
Field Measure
Add / Subtract
—
—
Convert to Total Inches
—
—
Fraction → Decimal
—
—
Decimal → Fraction
—
—
Panel Organizer
Upload a panel photo, build a paired left/right schedule, then print or save it. Multi-pole breakers reserve the next spaces on the same side automatically.
Photo Preview
🖼
No photo yet
Uploaded photo will preview here.
Panel Schedule
📋
No schedule built yet
Fill in the info above and tap Build Schedule.
Print lets you print or save as PDF. Save to Files downloads a clean HTML copy of the current schedule with the photo and your typed labels.
🌎
Grounding & Bonding
NEC-driven sizing for every ground you pull
EGC
GEC
MBJ
Supply-Side
SDS
Ground Rods
NEC Table 250.122How this works
Looks up the breaker or fuse in Table 250.122 (round up to the next row). In parallel runs, every raceway or cable gets its own full-size EGC sized off that same breaker — 250.122(F). If the hots were upsized for voltage drop, the EGC goes up by the same proportion of circular-mil area — 250.122(B). The EGC never has to be larger than the circuit’s own hots (250.122(A)).
NEC 250.66 · 250.28(D) · 250.102(C)(1)How this works
All three are sized from the largest ungrounded service conductor (for parallel sets, the total circular-mil area). GEC: Table 250.66, but the run to a rod/pipe/plate never needs to be bigger than #6 Cu / #4 Al (250.66(A)), to a concrete-encased electrode never bigger than #4 Cu (250.66(B)), to a ground ring never bigger than the ring conductor (250.66(C)). Main bonding jumper (250.28(D)) and supply-side bonding jumper (250.102(C)) use Table 250.102(C)(1); above 1100 kcmil Cu / 1750 kcmil Al they must be at least 12.5% of the service conductor area. With parallel sets in separate raceways, each raceway gets its own supply-side bonding jumper sized from the conductors in that raceway (250.102(C)(2)).
NEC 250.28(D)How this works
The main bonding jumper (MBJ) connects the service-neutral to the equipment ground at the service disconnect. Per NEC 250.28(D), MBJ sizing follows the same table as the GEC and is based on the largest ungrounded service conductor. For services over 1100 kcmil copper or 1750 kcmil aluminum, size per 12.5% of the largest phase area.
⚡
No result yet
Pick the service wire size and material above.
NEC 250.102(C)How this works
Supply-side bonding jumpers live between the service neutral and enclosures ahead of the service disconnect (like meter cans and CT cabinets). Per NEC 250.102(C), they're sized from the largest ungrounded supply-side conductor using the GEC table, then upsized proportionally for parallel runs based on circular-mil area.
⚡
No result yet
Pick the supply-side wire size and material above.
NEC 250.30(A)How this works
System bonding jumper (X0 to the enclosure) per 250.30(A)(1) using Table 250.102(C)(1). The SDS grounding electrode conductor per 250.30(A)(5) using Table 250.66. Both are based on the largest derived ungrounded conductor (total area for parallel sets). Electrode-type limits from 250.66(A)–(C) still apply to the GEC.
NEC 250.53(A)(2)How this works
The 25-ohm rule: if a single rod electrode reads over 25 ohms to ground, NEC 250.53(A)(2) requires a supplemental electrode. Most installations default to two rods regardless of test results, which satisfies the rule without measuring. Rods must be at least 6 feet apart (8 ft is typical). This tool compares your measured resistance and rod count against the rule.
⚡
No result yet
Enter your measured ohms and rod count above.
🔧
Torque
Field averages when the label's missing or rubbed off
Display units: lb-ft
Display units: lb-ft
NEC 110.14(D)How this works
NEC 110.14(D) requires every termination to be torqued to the manufacturer's spec. If the equipment, lug, or connector has a printed value, that wins — always. This tool exists for the moments when that label is missing, rubbed off, or too small to read in the field. Values shown are industry field averages with a ± 10% typical range. Bolt torque also shifts with lubrication, plating, and washers, so treat these as planning guidance only.
🔧
No torque value yet
Pick a termination type and wire size above.
📋
Estimator Pro
Build pro-looking quotes in 60 seconds
⚡ Pro Mode • Full Breakdown
Running Total
$0.00
—
20%
Show Profit on Customer Quote
Internal only. Keep OFF when sharing.
Line Items
0 items
Electrical Quote
Job: —
Quote ID: —
Date: —
PRO QUOTE
⚡ Final Total
$0.00
Material$0.00
Labor$0.00
Extras / Tax$0.00
Profit$0.00
📋 Scope of Work
(see onsite notes)
⚡ Valid for 30 Days
Estimate only. Final pricing may change due to site conditions, permit requirements, AHJ, and material market changes.
+ Add Work
✏️ My Prices
Saved on this device. New lines use these prices; lines already on a quote keep theirs.
Add your own item
📁 Quote History
⚙️
Command Center
Account, billing, legal, and support — all in one place.
⚡ Account
👤
Welcome, Sparky
@your_handle
FREE
📅 Certification
💳 Billing
📋 Legal
💬 Support
🌐 Website & Social
ℹ️ About
⚡
App Version
AmpStack · Busbar beta
⚠️ Danger Zone
📋
Title
Last updated
Content
📓
Job Journal
Daily logs, photos, customer notes — never lose a job detail again.